Construction and early works for the main treatment plant at Firestone Diamonds’ Liqhobong Diamond Mine, in the Lesotho Highlands, will commence in early 2014, when funding for the project is finalised.

Construction and commissioning of the main treatment plant will take two years, with full production scheduled to commence in early 2016.

The revised total initial capital cost is $185.4 million, an 11% increase, with an additional $5 million earmarked for grid power. The power component of the project is expected to take 13 months to complete, with grid power in place by July 2015.

The pilot plant has been in operation since June 2011, and has produced 300 000 carats of diamonds to date. With an estimated 90 mt at an average grade of 34.3 cpht, containing 31 million carats, Liqhobong is believed to be the third-largest undeveloped kimberlite resource as measured by contained carats, after the Gahcho Kue and Star kimberlites in Canada.

It is also the fourth-largest as measured by tonnes, after the Star and Orion South kimberlites in Canada and the Gope kimberlite in Botswana.

In terms of mine operating costs, the total cost per tonne of ore processed is $14.09/t. Improved diamond pricing of $107/carat confirms the robust economics of the mine, where large stones (plus 100 carats) are anticipated.

Firestone has just released an updated Definitive Feasibility Study (DFS) for the project, confirming its status as “a world-class diamond project that will yield very good returns for all of its stakeholders,” said Stuart Brown, incoming CEO.

“Alongside the increased diamond values, our updated numbers further management’s long-held belief in the compelling economics of the project,” confirmed Brown.

 

 

 