Production at Northam’s Zondereinde mine was slashed by almost 30% to 3 477kg (H1 F2013: 4 889kg), it reported in its results for the six months ended 31 December 2013.
However, PGM sales were less severely hit owing to release of inventory build-up during the Zondereinde smelter rebuild, which took three months, from June to October 2013.
Poor ground conditions
The additional revenue from these sales contributed to the mine breaking even at an operating level. Mining conditions at Zondereinde continue to be impacted by poor ground conditions, particularly on the Merensky reef.
This has been exacerbated by the downtime occasioned by the strike and requires slow and careful mining start-up activities. Steady progress has been made with the decline project, including initial stoping from 15 level.
The industrial action had little effect on the rate of capital expenditure, which consumed R243.5 million, with the smelter rebuild and the deepening project being the main capex items.
Labour relations
Wage negotiations at Zondereinde started on 31 July 2013. From the outset the negotiations were challenging and marked by disputes.
Following the intervention of third-party facilitators and extensive talks, the NUM was granted a certificate of non-resolution and proceeded with strike action with effect from 3 November 2013.
The strike continued for 79 days beyond the end of the reporting period until 21 January 2014. Losses amounted to 48 000 oz of PGMs and revenues of R750 million, while employees lost R151 million in wages.
The settlement reached included increases ranging from 7.5% to 9.5%, along with an ex gratia payment of R3 000 per employee.