The development of Phase 1 of the Mayoko project continues to progress, Exxaro has reported in its 2013 results.
Additional exploration has focused on improving the confidence of the banded iron formations at Lekoumou and Mipoundi.
The exploitation licence for the Mayoko project was issued by the Republic of Congo government during H2 2013.
The mining convention, Port Autonome de Pointe Noire Memorandum of Understanding, as well as the rail framework agreements with Chemin de fer Congo-Océan, were signed in Brazzaville on 29 January.
Negotiations will continue during the first quarter to finalise the outstanding commercial terms in order to execute all the necessary agreements.
A revised phasing plan and budget for the project will then be presented to the board in order to consider an investment decision.
Capital expenditure on developing the Mayoko project for 2013 was R1,6 billion, bringing total capital expenditure since acquisition to R2 billion.
Meanwhile, a bankable feasibility study for the ferrosilicon expansion project was concluded in 2013.
The start of the expansion project has been approved, and is scheduled for H1 2014, with commissioning of the additional plant expected in the second half.
Following a shutdown of the demonstration facility in Q3 2012, the AlloyStream Letaba project (a 50:50 JV with Assmang) resumed as planned in 2013, with the second campaign aimed at validating performance and scale-up. This is scheduled for Q1 2014.