Wesizwe’s Bakubung Platinum Mine will achieve full production 26 months earlier than planned, following an optimisation study approved by the board on 12 March.

The initial 230 ktpm production level is now planned for October 2020, as opposed to December 2022.

An 8.7% increase in mine capacity to 250 ktpm of run-of-mine ore at full capacity is now envisaged.

Steady-state monthly production will be boosted to 35 280 oz 4E / month or 420 000 oz 4E / annum, which equates to a 20% increase in the annual production rate.

This “significantly improved” ramp-up timeframe to full production is expected to slash the project’s nominal capex cost from R12.03 billion to R10.69 billion, COO Paul Smith told an investors and media briefing.

“The net change in project net present value is a positive R2.1 billion to R6.5 billion,” said Smith.

The significantly lower off-reef development will result in “substantial” savings of R1.1 billion.

Smith added that “an increase in expected operating costs over initial estimates” due to increased labour and power costs “had been factored in”.