The Bakubung Platinum Mine optimisation study was approved by the Wesizwe board on 12 March, it has reported.
COO Paul Smith told an investors and media briefing that 17% of the total project had been completed to date, with the main and ventilation shafts having reached depths of 396 m and 567 m respectively.
“Given that the mine development is currently in its shaft-sinking phase, an opportunity arose to undertake the optimisation study, without negatively affecting the development of the mine,” said Smith.
This was undertaken the improve the business case of the mine significantly in the light of lower platinum prices and rising cost pressures.