Basil Read-Matomo has been contracted to design, procure and construct the Evander Tailings Retreatment Project (ETRP) for Pan African Resources.

The company also constructed Pan African’s Phoenix Chrome Tailings Retreatment Plant, as well as its Barberton Tailings Retreatment Plant.

In addition, it completed the ETRP feasibility report and plant capex forecast. Fraser Alexander completed the Tailings Storage Facility (TSF) feasibility report and associated capital forecast.

Re-mining operation

Fraser Alexander will construct the TSF and operate the re-mining operation. Long-lead items such as leach tanks and carbon regeneration kilns are currently being procured.

Civil work of the ETRP is planned to commence in April 2014, with re-mining and plant commissioning commencing in January 2015.

Build-up

Build-up to full production is anticipated by June 2015. The expected electric power requirement of the ETRP (2800 KWhr) will be sourced as part of the current Kinross plant power reticulation.

The project should provide full time employment for an additional 20 workers upon completion.