The stacker and reclaimer assembly at the coal stockyard at Eskom’s Kusile project is planned to be commissioned this year, the utility says in a new report.

The first unit of what has been billed as the world’s largest coal-fired power station is scheduled for completion in Q4 2015. The overall project is 54% complete, while construction on Unit 1 is halfway finished, Eskom confirmed in a new-build progress report released this week.

The other units will be commissioned at approximately eight-month intervals, with the last unit expected to be in commercial operation by 2018, says Eskom.

The boilers on units 1 and 2 are 40.2% and 17.6% complete respectively, while silo construction is 93% complete. Main civil works are 70.8% complete and coal stockyard materials handling is 17.6% complete.

Kusile, based in Mpumalanga, will also be the first power station in South Africa featuring flue gas desulphurisation. This technology is used to remove oxides of sulphur, like sulphur dioxide, from exhaust flue gases in coal plants, in an effort to reduce emissions.