Jubilee is commissioning a third arc furnace at its Middelburg smelter operations, with the first hot metal load targeted for 17 April.
“This phase of our smelter operations renewal programme is the final step in establishing a sustainable operation with positive earnings,” said Jubilee CEO Leon Coetzer.
“I would like to congratulate our smelter operations personnel, engineering contractors and support services for their tremendous team effort to conclude the construction and refurbishment.”
The four-phase smelter renewal programme was spread over two years. The construction site flooded in March, leading to the suspension of all civil works.
Coetzer the company mitigated the impact of this delay by doubling the on-site engineering team and extending its working hours.
The furnace building and smelter aisle were also upgraded to better protect the operation from similar adverse weather conditions in future.