The expanded flotation circuit at Randgold Resources’ Tongon gold mine in Côte d’Ivoire is scheduled to be commissioned at the start of 2015.

“Tongon has made good progress in dealing with a number of technical challenges, but the issue of lower-than-expected recoveries is still being addressed,” chief executive Mark Bristow said at a media briefing.

“As we have reported before, this requires the expansion of the flotation circuit, which is scheduled to be commissioned at the start of 2015. The associated pressure on throughput and costs will have to be managed carefully,” commented Bristow.

Challenge in reaching consistent availability

Challenges in reaching consistent availability in the crushing plant resulted in a joint decision with Sandvik to change the current equipment to conventional Sandvik CH660 cone crushers.

“Randgold is working closely with Sandvik to combine the replacement with an upgraded flow sheet, including additional equipment and circuits to achieve the required capacity with an improved performance,” said Bristow.