The go-ahead for the Tasiast expansion project in Mauritania, West Africa “is not expected to be made until 2015 at the earliest,” Kinross CEO J. Paul Rollinson said in the company’s Q1 14 results.

A number of activities are being pursued to enhance the viability of the expansion plan, said Rollinson.

These include: exploring opportunities to further reduce capital and operating costs; measures to reduce execution variability in supply chain, logistics, contracting and labour in the construction phase; solidifying investment conditions in Mauritania; and continuing to explore additional mineral resource potential within the mine’s footprint, and along the 80 km Tasiast trend.

Improvement programmes

Tasiast achieved record quarterly production in Q1, mainly due to higher grades and mill throughput. Production cost of sales per ounce decreased 9% compared with Q4 2013, due to continuous improvement programmes.

These include a new truck shop, which increased maintenance efficiencies, and a new, lower-cost power plant, which replaced multiple high-cost generators.