Aveng Water has boosted the performance of the typical three-stage HiPRO plant, transforming this into a flagship product for the industrial-scale treatment of mine water.
As competition in the acid mine drainage (AMD) treatment sector starts to gain momentum, Aveng Water realised that the original HiPRO plant had to be modified if it wanted to stay at the cutting-edge of technological development in the sector. “We took it upon ourselves to stay as far ahead of the competition. Aveng Water is in a fortunate position to have plants in operation, so process optimisation and continual improvement is possible,” says process engineer Ashton Drummond.
Operational plants are currently treating over 35 Mℓ/day at recoveries in excess of 98%, with an additional 45 Mℓ/day coming online in the next year. The extremely high water recovery rate makes HiPRO an attractive option for the mining industry, as competitors not only have lower recoveries, but these also result in a brine stream that can ultimately pose an even larger problem.
Aveng Water developed the gypsum reactor at the heart of the HiPRO process. The removal of sparingly soluble salts allows the operation of more than one membrane stage to increase water recovery, while limiting the osmotic pressure required on these subsequent stages. Through research and development efforts, a large amount of information has been gained regarding the chemistry and operation of these reactors. Aveng Water prides itself as the market leader in gypsum reactor technology.
HiPRO solution
The HiPRO solution has now evolved to a superior process design which looks at the operational difficulties associated with the typical three-stage HiPRO plant, and solves them. The process design delivers a tried-and-tested HiPRO plant with:
• superior stability
• decreased process sensitivity
• reduced footprint
• decreased membrane area
• fewer pieces of equipment
• reduced energy usage
• reduced capital cost.
Aveng Water found that, when looking at options to increase plant performance while decreasing capital cost, two options were evident: either optimise the original HiPRO design, or try one of the various other AMD treatment options. In terms of a 20-year lifecycle costing for a water treatment plant, nothing competes with the optimised HiPRO process.
Modular designs
There has been a market-driven requirement to design and deliver smaller (5 Mℓ/day and less) AMD plants in timeframes that would not allow for large civil works, as was typical for large-scale HiPRO plants. Aveng Water has developed modular designs that drastically reduce design and construction time on future projects, as well as minimising the plant footprint, while still offering the award-winning process and reliability expected from the optimised HiPRO solution.
The water qualities that Aveng Water are currently treating range from a neutral pH, with high calcium, sulphate, magnesium and sodium levels, to more acidic waters with pH values as low as 2.0. These low-pH waters with excessive levels of dissolved iron and manganese come with many process-engineering design problems. Aveng Water has recently developed and implemented a novel process to deal with these extremely acidic waters, with the impressive addition of treating the water with zero brine production.
Aveng Water’s unrivalled technical acumen is backed up by safety standards that any company would be proud of. The Aveng Group is an industry leader in safe operating practices, and Aveng Water is committed to providing the best possible working conditions for all its employees, visitors and contractors. Its SHEQ programme meets the requirements of the OHSAS 18001 international standard, and it is currently gearing up for ISO 14001. Further to that, the Aveng Water directorate has authorised a quality management system, and subscribes to the principles of the ISO 9001 quality management framework.
Operations and maintenance
Aveng Water’s Operations & Maintenance Division (Aveng Water O&M) was previously incorporated together with Aveng E+PC Operations, a division of Aveng E+PC Engineering & Projects Company, which was formed in 1991. Combined, it has eight current outsourced O&M contracts, having successfully completed a further fifteen.
Within Aveng Water O&M, the current five plants being operated and maintained on an outsourced basis are the eMalahleni AMD water reclamation plant, the Optimum Colliery AMD water reclamation plant, the Kromdraai modular AMD water reclamation plant, the Erongo seawater desalination plant in Namibia and the Lephalale methane gas water plant.
Aveng Water continues to push the boundaries in the water-treatment sector, and stays true to the company vision of being the water-treatment solutions partner that focuses on innovation and agility in servicing its clients, leaving behind a positive legacy.