Junior platinum miner Wesizwe has ramped up shaft-sinking efforts and improved capital efficiency following an optimisation project at its flagship Bakubung project.

Shaft sinking of both the main and ventilation shafts is currently ahead of schedule, which will be followed by the imminent cutting of the first station on the ventilation shaft, all counting as major milestones in the development of the Bakubung mine.

Wesizwe highlighted these milestones in a media site visit to the Bakubung mine on Friday, when Wesizwe projects executive, Jacob Mothomogolo, told Mining News that he expects to reach the Merensky Reef within the next four to five months.

Mothomogolo says that the optimisation plan was commissioned in order to find opportunities to improve the business case for the mine. “One of the reasons we embarked on the optimisation programme is the changes taking place in the industry,” he explained.

These changes include fluctuating metal prices, increase cost pressures and challenging work conditions and social climate, noted Mothomogolo.

New shaft completion dates

A new completion date for the main shaft sinking was set for October 2015, 85 days earlier than the initial date of January 2016, and similarly the ventilation shaft is set to be completed 72 days earlier than the initial date of February 2017.

“The results of the optimisation showed that it was no longer necessary to have a shaft pillar as we did in the bankable feasibility study (BFS). As a result, the main shaft sinking and the ventilation shaft sinking operations will be completed months earlier than expected,” said Wesizwe GM Eddie Mohlabi.

Life-of-mine extended

Wesizwe now anticipates earlier production following its optimisation project, with the life-of-mine also being extended as a result of the optimisation project.

Mohlabi said that the reef tonnes per month had also be revised from 230 000 t/m to 254 945 t/m at full production, with more ounces expected per month in the early years.

The Bakubung had a total capital expenditure increase of R268 million, which Mohlabi says “came as a result of ensuring good production through the life-of-mine”.

The current net project value for the Bakubung project is R4.64 billion, which is derived from a 26-month shorter ramp up period.

The current focus of project development work is to improve shaft sinking rates, station breakaways, station and level development and further optimisation work regarding ventilation and compressors.