South African-based diversified resources group, Exxaro, advised its shareholders on Tuesday that there would be an impairment of the company’s investment in the Mayoko Iron Ore project in the DRC.
Exxaro said it would write-down a total of R5.362 billion in investments made in the project, which included the original acquisition cost of the investment and the project related development costs. The exact quantum of the impairment loss will be communicated as soon as calculations have been finalised.Concept study
In a media conference on Tuesday, Exxaro CEO Sipho Nkosi discussed the impairments as well as Exxaro’s future strategy in the project, saying that a concept study was undertaken on the project. The revised concept study for a 12 million tonne per annum operation inclusive of value engineering exercise for an optimised ramp up strategy was concluded during June 2014. “The results of the concept study indicate that the project is not economically viable, based on the revised assumptions,” said Nkosi.Alternative agreement
Nkosi said that all future expenditure on the project would be stopped with immediate effect until a revised negotiation alternative agreement was concluded on favourable terms, and which would support an economically viable project. Exxaro hoped to conclude definitive port and rail agreements for the Mayoko Project as communicated on 6 March 2014.Rail and port solution
Exxaro secured a signed mining agreement with the Republic of Congo that included a framework agreement for rail and port solution in the Mayoko project, which it acquired from African Iron in 2012.Based on the assumption that project agreements will be finalised in reasonable time frames, Exxaro acquired assets, such as rolling stock and harbour cranes and made executive appointments to permit fast track project development.
However, Nkosi said that the mining convention was not signed until January 2014, which is effectively 10 months after original submission. “There has since been slow progress on other required project agreements – most of which are still outstanding.” Nkosi said that Exxaro remained committed to a reaching a port and rail solution that will render the project economical viable in a clearly defined approach and timeline. “If terms and conditions concluded in the definitive agreement is favourable and the rail and port solution provides for an economically viable project only then Exxaro be in a position to consider the future of the project.”