Civil works have commenced on the second phase of the course ash conveyor structure at Medupi power station in Lephalale, Limpopo, Eskom has reported in the latest edition of its New Build News.

The 4 764MW power station is expected to have its first unit of 794MW completed by the second half of this year.

Technical milestones

“Medupi is on track, with several technical milestones being achieved,” Eskom stated. These included pressure testing of the super heater on 14 May.

This involved filling up the boiler with demineralised water that was steam-heated by the auxiliary boilers. The second round of inspections on 15 May revealed no leaks. The pressure was then reduced in order to be able to reopen the boiler for continued construction.

Link bridge

The Unit 5 to 4 link bridge was lifted into position on 18 May, following a two-day operation. “This achievement is very commendable, as the crew involved showed dedication and commitment to achieve key set dates,” said Eskom. Auxiliary steam blow-through began on 8 June.

Construction on the eastern seasonal stockyard began on 15 May, with 50% availability achieved by 6 June, including access ramps. Two thousand tons of coal was received.

Roshcon has begun the compaction works on the strategic stockyard, while the last main boiler frame at Unit 1 has reached 105.6m.