While not all of National Union of Metalworkers of South Africa’s (NUMSA’s) 220 000 members may have taken to the strike action in the metals and engineering sector, the effects of the strike were felt by power utility Eskom.

According to media reports, 800 out of an expect 1 800 employees turned up for work at Eskom’s Medupi power station on 1 July, when NUMSA called its members to down tools.

Construction disrupted

The construction sites of both the Medupi and Kusile power stations were reportedly disrupted by the strikes on Tuesday.

On Tuesday, the union’s strike began with a series of marches across the country in demand of the 15% wage increase.

NUMSA members were set to engage in a march on Wednesday in protest of a 5.6% wage offer that the power utility has tabled.

Wage compromise

Other stakeholders in the metals and engineering sector offered a seven to eight percent wage increase in response to NUMSA demand of a reduced 10.5% demand.

NUMSA’s leadership in Johannesburg subsequently reverted to the 15% demand viewing the offer as ‘arrogant’ by employees.

Medupi Power Station is a new R105 billion dry-cooled coal-fired power station being built by Eskom near Lephalale in Limpopo province, South Africa.

NUMSA was not able to say how much of its 220 000 members responded to the call for strike action.