Universal Coal has commenced with hot commissioning of the dense medium separation circuit of its Kangala mine’s washing plant, reports Platts Coal Trader.

The junior miner announced that full operations via the circuit are earmarked to start on 23 June, to be followed by thorough testing before it begins to produce export-quality thermal coal.

RBCT exports from July

Universal expects to commence with exports from Kangala from the Richards Bay Coal Terminal in July, it reports.

Universal’s 70.5%-owned Kangala Colliery is expected to produce 2.1 million mtps of saleable thermal coal, of which 2 million mpta will go to Eskom.

Meanwhile, Universal reports that its acquisition of the New Clydesdale Colliery from Exxaro was still being finalised. It would be combined with its adjacent Roodekop project in order to fast track  development.