Platinum Group Metals’ (PTM’s) Western Bushveld Joint Venture (WBJV) Project 1 platinum mine near Rustenburg could be adversely affected if the strike by the National Union of Metalworkers of South Africa (NUMSA) drags on.

Delayed or potentially stopped

The WBJV Project 1 could be delayed or potentially stopped for lack of supplies, equipment and consumables, PTM has warned.

To date, about 4.49 million man hours of construction work have been completed, and about $337 million has been invested in construction, equipment and underground development.

Underground development

Underground development has reached the Merensky Reef, and initial mining blocks are in detailed mine planning and early development.

Stockpiling of early development reef tonnes is underway. Crusher, mill, ore silo and flotation circuit foundations are substantially complete, and erection of structural steel has now commenced.

Mill components

Mill components have been ordered and are being fabricated with a number of items now complete. The primary mill shell, ends and trunions are on-site, as are most flotation and rougher circuit tanks.

Construction of the water pipeline from the mill to a nearby main supply line is in progress. A 10 MVA electrical supply was completed and energised in October 2013. Preparations for the next 10 MVA service are moving forward as planned.

Ventilation raises, fans

Two ventilation raises and fans are fully operational to support underground development. Underground mining of multiple declines and headings continues.

Capital costs have been in line with the cost budget estimate, and first concentrate production is targeted for calendar fourth quarter of 2015, in line with previous guidance.

“Underground development delays or delays in the delivery of key components or services could result in delays to the first concentrate production or ramp up,” PTM has warned.