The development of Resource Generation’s (Resgen) Boikarebelo mine will be delayed by three to six months as a direct result of its main earthworks contractor Protech Kuthele going into liquidation this month.
In July, Protech Kuthele Holdings removed all staff from the mine site and terminated all activities, including those of its subcontractor, which was building three bridges under and over the rail line. Coal production at Boikarebelo is now estimated to begin the first half of 2016.Waterberg coal reserves
The Boikarebelo mine is situated in South Africa’s Waterberg region, which has probable reserves of around 744.8 million tonnes of coal, accounting for 40% of the country’s remaining coal resources.In a statement, Resgen said that it is recommencing earthworks for the rail link, roads and incomplete terraces require detailed surveys to establish bill of quantities for retendering.