The development of Resource Generation’s (Resgen) Boikarebelo mine  will be delayed by three to six months as a direct result of its main earthworks contractor Protech Kuthele going into liquidation this month.

In July, Protech Kuthele Holdings removed all staff from the mine site and terminated all activities, including those of its subcontractor, which was building three bridges under and over the rail line.

Coal production at Boikarebelo is now estimated to begin the first half of 2016.

Waterberg coal reserves

The Boikarebelo mine is situated in South Africa’s Waterberg region, which has probable reserves of around 744.8 million tonnes of coal, accounting for 40% of the country’s remaining coal resources.

In a statement, Resgen said that it is recommencing earthworks for the rail link, roads and incomplete terraces require detailed surveys to establish bill of quantities for retendering.

Appointing alternative contractor

Resgen does not expect any difficulty in appointing an alternative earthworks contractor for a similar cost, but commercial prudence requires a diligent process to be undertaken, stated the company.

Resgen stated, however, that significant progress has been made at the mine. Stage one of the company’s mine development targets’ saleable coal production is at six million tonnes per annum.

Meanwhile, the Resgen reports that while negotiations on term sheets for project finance to complete the development of the mine had been protracted and were continuing, it had, during the three months ended June 30, made progress in terms of negotiations with three parties for the funding of mobile equipment valued at $100-million.