Gold miner Centamin second-quarter core earnings nearly halved as it mined lower-grade ore at its key Sukari mine in Egypt.

The company said core earnings, or earnings before interest, taxation, depreciation and amortisation (EBITDA), fell 49% to $32.6 million for the quarter ended 30 June from a year earlier.

Quarterly production fell 13% to 81 281 oz of gold compared to the same period in the year prior.

High production forecast

The company forecast higher quarterly production rates for the remainder of the year as plant throughput increases and underground grades improve.

Centamin said it would pay a maiden interim dividend of 0.87 cents per share.

New investment law

New investment law in Egypt came into force in April 2014 restricting the capacity for third parties to challenge any contractual agreement between the Egyptian government and an investor.

Centamin said that it understands, based on legal advice that it is likely to benefit from this new law.

Plant commissioning

Commissioning of the new Stage 4 plant proceeded well, with quarterly throughput at the Sukari process plant reaching a record 1 957 KT.

The plant is expected to ramp-up during H2 2014 to the expanded 10 Mtpa nameplate capacity, reports Centamin.

Full-year guidance

Successful commissioning activities resulted in the first material contribution from the Stage 4 plant expansion during the quarter, commented Centamin chairperson, Josef El-Raghy.

“Therefore, with both plant throughput and average grade set to increase during the remainder of the year, we maintain our full year production guidance of 420 000 ounces in 2014 and continue to look forward to delivering Sukari’s long-term target of 450,000 – 500,000 ounces per annum from 2015 onward,” he said.