Gold Fields will pilot two new techniques at its flagship South Deep mine as it tries to unlock value from the $50 billion gold reserve.

Speaking at an earnings presentation on Thursday, Gold Fields CEO Nick Holland said the new methods at South Deep, a fully-mechanised operation, were in a bid to meet a target of producing 700 000 oz a year at the site by around 2018.

Destress mining

Gold Fields is currently using a system called ‘destress mining’ in which horizontal cuts are made into the rock in such a way that a lot of the ‘stress’ that can cause rock bursts underground are removed.

This system also means opening up vast areas that require a lot of support, and so significant time and money can be spent before any bullion is extracted.

Inclined slot method

Holland said the company was experimenting with a variation of destress mining, as well as an entirely new way of doing things called the inclined slot method, which has been employed at its Australian operations.

“It is much quicker, easier and probably will be cheaper,” stated Holland. “It’s going to be a year for us to pilot it, assimilate all the results and determine the way forward.”

Geological challenges

Gold Fields has brought in a top Australian engineering team to help overcome the technical and geological challenges at South Deep, where delays and shifting production targets have annoyed investors.

The South Deep operation, with a bountiful 40-million ounce reserve, is one of the few gold mines in South Africa where sophisticated mechanisation is possible because the seam is so big – making it suitable for big machines.

Peru project sale

Meanwhile, Gold Fields agreed to sell its 52% stake in a company that manages the Chucapaca open-pit gold project in southern Peru to Buenaventura, that country’s largest precious metals mining company.

The agreed sale price is $81-million, to be paid by Buenaventura concurrently with the execution of the agreement, and a 1.5% net smelter royalty on future sales of gold, copper and silver produced in the current Chucapaca concession, announced Gold Fields.

Future upside

“We are pleased to have agreed terms with Buenaventura to sell our controlling stake in Chucapaca. The royalty agreement provides us with future upside, as we see Buenaventura, with its local expertise and experience, advancing this project fairly quickly,” stated Holland, in a company statement.

The acquisition price of $81-million and the royalty deal ensured that Gold Fields’ investments in the Chucapaca project are recouped, the company said.

“The sale of our stake is in line with our strategy of focusing on growing cash flow and moving away from greenfields exploration and new project development as a strategy for growth, in favour of the acquisition of in-production ounces and near-mine exploration and development,” commented Holland.