Canadian-listed Maya Gold and Silver on Thursday announced a successful first silver pour at the Zgounder Silver Mine in Morocco.

The miner said the pouring is the result of 17 days of operation of which 10 days were dedicated to mechanical testing with low-grade mineralised material and seven days of mineralised material from ‘ancient stockpiles’ on hand.

Silver recovery

Mill silver metal recovery achieved during this time was 86% following the processing of 2 876 tonnes from metallurgical balance at the mill.

The junior miner, based in Canada, aims to produce 85 000 oz silver/month in 2014. 

Significant achievement

“We are extremely pleased to achieve our first silver pouring following site and mill rehabilitation that started in September 2013,” commented Maya CEO Guy Goulet on the milestone at Zgounder.

He added, “This is a significant achievement for Maya and is a direct result of the outstanding efforts from all stakeholders led by our President, Noureddine Mokaddem, with the support of the local residents and thanks to the assistance of the relevant departments of the Moroccan Government.”

In a preliminary economic assessment the junior outlined an underground mine with a 10-year mine life that would produce about 1 million ounces silver a year.