Impala Platinum’s (Implats) performance over the past 12 months has been severely impacted on by the five-month strike and low metal prices.

The five month strike which ended in July this year resulted in lost production at Impala Rustenburg of 312 000 platinum ounces, stated the company in its results report for the 12 months ended 30 June.

Implats said it margins would be under pressure in the short- to medium-term owing to the effects of the strike and low metal prices.

Cost pressures

In a statement, Implats CEO Terrence Goodlace said that lower than expected platinum group metal prices, together with escalating cost pressures and the protracted strike, were all contributing factors to a ‘challenging year for Implats’.

A walkout by more than 70 000 miners at the South African operations of Impala, Lonmin and Anglo American Platinum (Amplats) cost the companies about $2.3 billion of stalled output during the stoppage that ended 24 June.

Amplats is seeking buyers for four mines and Lonmin warned of possible job cuts as it reviews operations in the wake of the strike.

Performance indicators

The key operational and performance setbacks include an increase in group unit costs by 17.6%, a decrease in headline earnings per share by 74%, and a 25% reduction in gross refined platinum.

Despite the challenges experienced during the period, Goodlace said the deliveries continued to the miners’ key customers during this period – particularly to the local South African market that remained adequately stocked during the strike.

The company’s operations outside the Rustenburg area, namely Zimplats, Mimosa, Marula and Two Rivers, all performed well and delivered good safety and operational results, noted Goodlace.

Project delays

The industrial action has led to delays in project and development build-up profiles, with ramp-up to normal production rates expected to take approximately four months, reports Implats.

The company will consider altering spending on three major shafts that would’ve accounted for more than a third of production from 2019 at its Rustenburg operation.

The stoppage delayed work on the projects, which also suffered because contractors had to be redeployed and cash had to be preserved, he said.

Rebuilding in Rustenburg

Goodlace said that Implats is rebuilding its Rustenburg operations and increasing volumes at other sites are on-going.

The company is also mitigating the effects of the closure of the Bimha mine at Zimplats, after a collapse of an underground portion of the operation in August.