Gold developer Bassari Resources is pleased to deliver positive results from a preliminary Underground Scoping Study based on high-grade underground gold production from its Makabingui Gold Project in Senegal, West Africa.

Bassari released positive results from a high-grade Open Pit Feasibility Study, which supports profitable high-grade gold production by initially mining 180 000 oz from four high grade pits, within the one million ounce Makabingui gold resource.

Further drilling

The preliminary Underground Scoping Study, based on Inferred Resources, encourages further drilling to expand the Indicated Resources used in the Makabingui Open Pit Feasibility Study.

Underground development is additional to opportunities along strike from open pits within the one million ounce resource and the much larger potential already identified at Makabingui South within the existing major gold corridor.

Significant potential

“The positive results of the underground scoping study further supports the significant potential that exists at Makabingui, which is already set to become Senegal’s next large scale gold operation.” Managing Director Jozsef Patarica said.

“Our focus on unlocking significant value from our gold resource is delivering outstanding results which we will continue to build on. We have taken a material step forward with this option to provide additional high grade mill feed that can extend the life of the operation to six years.

“The Board acknowledges the ongoing support of the Senegalese Government for the project in the lead up to mining. Makabingui is well on its way to becoming the second large scale gold mine in Senegal, a significant milestone for all shareholders, stakeholders and local communities.”

Mineral resource

The Makabingui Gold Project currently hosts a Mineral Resource, which comprises 11.9 million tonnes averaging 2.6 g/t gold for a contained 1 million ounces of gold classified into the Indicated and Inferred Resource categories.

The initial open pit mining phase focuses on the Indicated Resource based on a conventional gravity and Carbon in Leach (CIL) processing circuit. The Open Pit Feasibility Study for the initial mining phase delivered outstanding results.

Scoping study

The preliminary Underground Scoping Study has been undertaken by Australian Mine Design & Development (AMDAD).

The study provides an assessment of the potential for an underground development phase for the Makabingui Gold Project within the one million ounce gold resource. The combined Open Pit and Underground studies used a Mineral Resource made up of Indicated and Inferred resource blocks.

Exploration permits

Bassari holds a 70% interest in each of three contiguous exploration permits; Sambarabougou, Moura and Bounsankoba, covering approximately 850 km2 in a central location of the highly prospective Birimian Kenieba Inlier.

The permits are located approximately 750 km east of Senegal’s capital city of Dakar and about 70km north east of the town of Kedougou, and span 80km strike length of parts of a major crustal shear zone, the Main Transcurrent Shear Zone (MTZ), a well-defined gold mineralised structural corridor.

The Kenieba Inlier hosts several multi-million ounce gold deposits and extends into the bordering countries of Mali and Guinea.