Hebei Iron and Steel Group, of China and South Africa’s Industrial Development Corporation (IDC) $4.5 billion steel project is continuing apace, with a detailed feasibility study set to be completed in Q1 2015.
IDC CEO Geoffrey Qhena said the project would be developed in Limpopo Province and would draw its iron-ore resources from the magnetite tailings in the Phalaborwa area. Qhena was speaking at the State-owned development finance institution’s annual results presentation in Johannesburg on Thursday.Project funding
The $4.5 billion steel project will be rolled out in two phases, the first would cost R2.7 billion for 3 million tons by 2017. About R1.8 billion will be allocated to the second phase for 2 million tonnes by 2019. Both phases will be funded through a combination of debt and equity.Domestic excess capacity
Qhena said the international market will be target in addition to the domestic market, which had excess capacity, however, the mill would be target regional markets, he said. The first three-million-ton phase was expected to be completed by 2017 at a cost of $2.8-billion, with the second two-million-ton phase to be introduced by 2020 at a cost of $1.7-billion.