Shale gas exploratory drilling in the Karoo could get underway as early as mid-2016, according to South Africa’s Department of Mineral Resources (DMR).

DMR director-general Thibedi Ramontja told Parliament’s select committee on land and mineral resources on Tuesday that the draft regulations, once finalised, will result in a regulatory framework that will ensure safety in exploration and during the subsequent extraction of gas.

In addition, laws governing how shale gas will be extracted from the ecologically sensitive Karoo and other regions, will be published by the DMR in January next year.

Exploration schedule

Ramontja told the MPs that licences for companies to carry out exploration using fracking could be issued by July-August and that the actual commercial exploitation could start within 18 months after that.

The DMR intends to finalise the regulations in December and January and consultations with affected communities would be carried out.

Ecologists against fracking

Fracking in the Karoo is a controversial issue with ecologists saying it could destroy the pristine environment while communities say it would bring much- needed jobs and investment to a generally impoverished area.

Anti-fracking group’s Treasure Action Karoo Group (TKAG) has been in consultation with the DMR over a ‘flawed’ and biased feasibility study on fracking for shale gas in the Karoo.

Transparent investigation

TKAG believes South Africa should adopt a transparent and scientifically valid approach to the investigation of shale gas resources.

“We maintain an open mind about the ability of shale gas mining to match the claims of its proponents – if it is indeed the ‘game changer’ claimed by Shell et al, then those claims can be validated by scientific investigation, and a thorough cost-benefit analysis in which science can inform policy,” TKAG told Mining Ne.ws in an earlier report.

Karoo shale reserves

Deputy director-general for mineral policy Mosa Mabuza Mabuza has stated that the conservative estimate of shale gas reserves in the Karoo was 18-70-trillion cubic feet. The initial estimates were about 485-trillion cubic feet.

At least three companies are known to have applied for exploration rights. These reportedly include Shell, Bundu Oil & Gas, and Falcon Oil & Gas.

Mabuza told the Parliamentary resource committee that the exploration phase could span three-to-seven years.

Prospecting works programme

Companies looking to undertake shale gas exploration activities in the Karoo had to submit a prospecting works programme spelling out their planned activities, Mabuza said.

These involved initial desk-top studies and seismic work, after which drilling could commence.

Each step in this process was monitored by the department, which had to be satisfied before the company could move to the next.

It could take up to two years of exploration before a company struck a commercially viable well and it would be very lucky if a company made a commercial find with the first well drilled.