The Impala Platinum (Implats) and Aquarius Platinum-owned Mimosa mine will undergo a $40 million expansion project in the next five years.

This will extend the lifespan of the Mimosa – the second largest platinum mine in Zimbabwe – by 20 years, according to reports.

Expansion plan

In its annual report for 2014, Aquarius Platinum said the expansion project will see operations extended to the Mtshingwe block.

“This will entail on-reef development. The total cost of the revised project is $40 million over five years and includes additional mill capacity and an upgrade to the crusher, additional fully equipped production teams and a ventilation upgrade,” said the group.

Aquarius said the development from the existing decline shaft began in July and is expected to take four years to complete by which time it will have reached the Mtshingwe axis.

Capital expenditure

Aquarius said total capital expenditure at Mimosa for the year amounted to $34 million.

“Expenditure was incurred mainly on the purchase and maintenance of mobile equipment, drill rigs and LHDs, the conveyor belt extension and down-dip development, the milling and flotation project and the refurbishment of the primary jaw crusher.”

During the year Mimosa retrenched 103 employees and 34 managers on a voluntary basis, about 8% of its total labour force.

“The reduced number of employees will contribute to an estimated decrease in costs of five percent overall,” said Aquarius.

Mimosa’s fourth quarter production of more than 60 000 PGM ounces was the mine’s highest ever level production, announced the company.