The Impala Platinum (Implats) and Aquarius Platinum-owned Mimosa mine will undergo a $40 million expansion project in the next five years.
This will extend the lifespan of the Mimosa – the second largest platinum mine in Zimbabwe – by 20 years, according to reports.Expansion plan
In its annual report for 2014, Aquarius Platinum said the expansion project will see operations extended to the Mtshingwe block. “This will entail on-reef development. The total cost of the revised project is $40 million over five years and includes additional mill capacity and an upgrade to the crusher, additional fully equipped production teams and a ventilation upgrade,” said the group. Aquarius said the development from the existing decline shaft began in July and is expected to take four years to complete by which time it will have reached the Mtshingwe axis.