Global diversified miner Vedanta Resources announced a $782 million investment in a zinc project in the Northern Cape, South Africa over the next three years.

Vedanta, which already operates the  Black Mountain copper mine in the country, will replace output from its soon-to-be-closed Lisheen operation in Ireland, with its new Gamsberg zinc mine in South Africa.

The Gamsberg mine, at Aggeneys in the Northern Cape, will cost $630 million and produce 250 000 tonnes a year of zinc in concentrate.

Processing in Namibia

According to reports, Vedanta will truck 150 000 tonnes of zinc-and manganese-rich concentrate to its Skorpion zinc refinery in Namibia to process into metal.

The remaining 100 000 tonnes of concentrate will be sold on the open market. Vedanta will spend $152 million on converting the Skorpion refinery to treat the sulphide concentrate coming from Gamsberg, about 360 km away, said Vedanta’s Africa Metals Business CEO Kishore Kumar.

Anticipated production

Vedanta Group CEO Tom Albanese, in a company statement, said the Gamsberg–Skorpion integrated zinc project is central to Vedanta’s long-term aspirations for Southern Africa.

“The output from Gamsberg, coupled with extending the life of the world-class refinery at Skorpion Zinc, in Namibia, will make the Southern African region one of the most important suppliers of refined zinc globally.

“That will also result in these operations forming one of the cornerstones of our operations in Africa and will partially offset the loss of volume resulting from the end-of-life of mine at Lisheen, in Ireland,” commented Albanese.

Operating company

Black Mountain Mining, in which London-listed Vedanta’s Sesa Sterlite subsidiary holds 74% and South Africa’s Exxaro Resources 26%, would operate the Gamsberg–Skorpion project.

The investment decision was made following the presentation of a detailed feasibility study for the mining project to Vedanta’s board.

Work was already under way to establish a pilot plant for the refinery conversion, while preliminary work on financing options had started.

Gamsberg Phase one

The first phase of the Gamsberg open-pit mine was estimated to have a 13-year life span, with the first ore likely to be produced in 2017/18.

About 1 500 jobs will be created during the construction phase, while the mine would provide employment for 500 employees once operational.

Eskom supply agreement

The new open-cast project will be started in the first quarter of next year and will need 40MW of power, for which Vedanta had reached a supply agreement with Eskom, according to reports.

In three to five years there will be mine closures in Australia and Canada, as well as Lisheen, said Kumar. “Three or four of those closures are significant suppliers, so timing-wise we are well positioned at Gamsberg.”