Canadian gold mining junior True Gold expects to pour gold at its Karma Gold Project in Burkino Faso by the end of 2015.

The Toronto-listed miner said on Monday it is on schedule to produce 160 000 oz gold in 2016 at its Karma heap-leach project.

Thus far, the company has spent $51.5 million, or 39% of a $131.5 million capital expenditure budget.

Construction progress

True Gold’s President and CEO Dwayne Melrose said that the construction continues at a strong pace with the mine now beginning to take shape.

True Gold has $49 million in its treasury and will draw down on a $100 million in financing with Franco-Nevada and Sandstorm, royalty/streaming companies to cover the rest of capital costs.

To date, all aspects of the Project are on time and on budget, states the company.

Additional Mine Development Details

  • The Company expects Karma to produce approximately 150 000 ounces gold in 2016
  • Key personnel are in place; recent hires include the Mine Superintendent and the Mine General Foreman
  • Procurement was 33% complete at the end of October, ahead of the planned 23%
  • Earthworks on the plant site terraces are complete, one month ahead of schedule
  • Civil works were 20% complete at the end of October, ahead of the planned 14%
  • Work has started on foundations for the ADR plant, cement storage facility, and maintenance shop
  • Administration, security and medical buildings are built; mine offices are 90% complete
  • Two dozers and two graders, part of the mining fleet, were delivered to site 11 November
  • All mining fleet vehicles and equipment are expected on-site by January 2015
  • Major earthwork projects, haul roads, raw water storage pond and the base for the heap leach pad will begin in January 2015

Mine-building team

“We have an exceptional mine-building team in Burkina Faso, which includes more than 200 people from local communities,” commented Melrose in a company statement.

He added, “” The capacity of this team to work efficiently and cost-effectively has increasingly become a competitive advantage for the company.”

Next to go into production

Karma is fully funded and permitted, and is one of a select few gold mines under construction globally. It is scheduled to be the next gold mine to go into production in Burkina Faso.

During mine operations, True Gold will employ over 400 people at Karma.

True Gold reports that pre-stripping of the Rambo Deposit, Karma’s highest grade deposit and the first to be mined, will begin in December 2014.

Additional Reading?

Request Free Copy