Canadian gold mining junior True Gold expects to pour gold at its Karma Gold Project in Burkino Faso by the end of 2015.
The Toronto-listed miner said on Monday it is on schedule to produce 160 000 oz gold in 2016 at its Karma heap-leach project. Thus far, the company has spent $51.5 million, or 39% of a $131.5 million capital expenditure budget.Construction progress
True Gold’s President and CEO Dwayne Melrose said that the construction continues at a strong pace with the mine now beginning to take shape. True Gold has $49 million in its treasury and will draw down on a $100 million in financing with Franco-Nevada and Sandstorm, royalty/streaming companies to cover the rest of capital costs. To date, all aspects of the Project are on time and on budget, states the company.
Additional Mine Development Details
- The Company expects Karma to produce approximately 150 000 ounces gold in 2016
- Key personnel are in place; recent hires include the Mine Superintendent and the Mine General Foreman
- Procurement was 33% complete at the end of October, ahead of the planned 23%
- Earthworks on the plant site terraces are complete, one month ahead of schedule
- Civil works were 20% complete at the end of October, ahead of the planned 14%
- Work has started on foundations for the ADR plant, cement storage facility, and maintenance shop
- Administration, security and medical buildings are built; mine offices are 90% complete
- Two dozers and two graders, part of the mining fleet, were delivered to site 11 November
- All mining fleet vehicles and equipment are expected on-site by January 2015
- Major earthwork projects, haul roads, raw water storage pond and the base for the heap leach pad will begin in January 2015