AIM-quoted diamond development company, Firestone Diamonds plc has released an update for the Liqhobong Diamond Mine, which is owned 75% by Firestone and 25% by the Government of Lesotho.

Project Update
Construction at Liqhobong continued in earnest during the quarter ending 31 March 2016. Activities were helped by the granting of further work permits by the Government of Lesotho and the favourable weather conditions experienced at site in recent months. Firestone said it continues its water storage activities and now has in excess of 500,000 cubic metres of water on site, sufficient for the first year of production, thus de-risking the project further by mitigating one of the critical early start-up risks.

As previously announced all significant civils and earthworks have now been completed and in December 2015, the site was handed over to the structural, mechanical, plate and pipework contractors for the erection of the main plant, the company indicated in a statement.

As a result a number of project areas have since been completed or are over 98% complete including the RSF starter wall, the design, engineering and procurement elements alongside the structural steel fabrication. Firestone said as expected the detailed mine planning continues to be refined and reviewed as the Project progresses towards production.

“Operational readiness, led by the project team, is well underway and the team’s main focus during this quarter was contract placement and staff recruitment,” the statement reads.

General view of the Main plant terrace from South side

General view of the Main plant terrace from South side

Throughout Liqhobong’s development Firestone said it has enforced a rigorous safety policy and has continued to maintain its lost time injury free record, with approximately 2.2 million man hours worked as at the end of March 2016.

As at the end of March 2016, the project was 72% complete and in line with the revised construction schedule. The project also remains within the original US$185.4 million budget and as at 31 March 2016, ZAR1.5 billion (US$129.9 million) or 70% had been spent on the project against the revised capital budget of ZAR2.1 billion. The cash on hand at the end of March 2016 was US$14.8 million and the company also had US$47.0 million available pursuant to the ABSA debt facility, resulting in forecast headroom available to the Firestone of approximately US$9.0 million as at the end of December 2016, which does not include the US$15.0 million standby facility available to the company.

“Firestone has achieved another strong quarter of progress at Liqhobong, which, as at 31 March 2016, was 72% complete and on track for initial production in Q4 2016.

Liqhobong diamond mine, located within the Liqhobong valley in the Maluti mountains, approximately 120km east-northeast (ENE) of the capital city of Maseru.

Liqhobong diamond mine, located within the Liqhobong valley in the Maluti mountains, approximately 120km east-northeast (ENE) of the capital Maseru.

Firestone remains fully funded to completion of the project, production ramp up and the first sale of its Liqhobong diamonds and I look forward to providing further updates as we move towards project commissioning in Q4,”  Stuart Brown, Chief Executive Officer, commented.

 