First Quantum Minerals Ltd (FQM) has submitted an application to the Botswana Ministry of Finance for a Manufacturing Development Approval Order for the Sese Integrated Power Project.
The minerals company has committed AUD $3 million over the next twelve months on work programs to advance the Sese Project.
Since drilling commenced in September, five geotechnical holes have been drilled over the planned Sese power station site to evaluate soil and bedrock strength for power station footings, and four large diameter holes have been drilled to provide new data to finalise a power station fuel specification and undertake combustion testing at Eskom’s labs in South Africa.
The company is looking to start geotechnical evaluations of the proposed power station site and begin with the preliminary power station design and layout.
FQM are required to commit a further A$9.4M by 12 July 2017 to acquire an additional 20% interest in the project.