Harmony Gold Mining’s planned shutdown at its Hidden Valley mine in Papua New Guinea (PNG) has been completed two weeks ahead of schedule and processing of ore recommenced mid November, according to the miner.
“It is expected that commercial levels of production will be achieved in the June quarter 2018, as per plan.”
Davies highlighted at the conference that safety at the mine is industry leading, with a lost-time injury rate during the past twelve months of 0.2 per million hours worked and the last lost-time injury recorded in April 2017. “The Hidden Valley team showcases responsible mining – communities benefit, employees benefit and the mine is well on track to deliver annual steady state gold production of 180 000oz at an all-in sustaining cost of less than US$950/oz during FY19”, said Peter Steenkamp, chief executive officer of Harmony.