Eskom says it is currently considering Optimum Coal Mine’s business rescue practitioners’ proposal to reduce the monthly coal supply tonnage to the Hendrina power station from 400 000 to 200 000 tonnage.
The power utility emphasised that it has not agreed to any price adjustment with the business rescue practitioners and the allegations made in a newspaper article on Sunday are factually incorrect and without basis.
“Should Eskom decide to accept any reduction of the coal supply tonnage, as proposed by the business rescue practitioners, such will be done at the current coal supply contract price,” it said. The utility is not in possession of the business rescue plan, however, can confirm that it has requested the plan so it can engage amicably as an affected party. In January, the mine, owned by the controversial Gupta family and former President Jacob Zuma’s son Duduzane, failed to meet its contractual deliveries to Hendrina.