Gold exploration company Perseus Mining has updated its mineral resource estimates at its Edikan Gold Mine (EGM) mining leases in Ghana following the completion of an in-fill drilling programme.

The mineral resource estimates were updated by independent consultant RungePincockMinarco in accordance with the JORC code 2012, reports Perseus Mining.

Deposits at Edikan

The mineral deposits identified on the EGM tenements at the Edikan site were calculated using a 0.40 g/t gold cut-off grade.

Perseus reports that the updated mineral resource contains 357 300 fewer ounces of gold in the measured and indicated categories and 74 300 fewer ounces in the inferred category – relative to the previous mineral resource estimate for EGM published in June 2013.

After adjusting both mineral resource estimates to the mining surface as at 30 April 2014, the net decrease in mineral resources is 155 500 oz (2.8%) in the measured and indicated category and 73 800 ounces (3.0%) in the inferred category.

Revising the pit design

Work is underway on revising the design of each of the pits based on the updated mineral resources, as well as key operating parameters, and reassessing the sequence in which each of the pits will be brought into production, with the objective of maximising cash flow generated by the Edikan operation.

The revised Life of Mine (LoM) plan and updated ore reserve statement is expected to be completed in the December 2014 Quarter.

Resource assumptions vs actual conditions

EGM MD Jeff Quartermaine says that the update mineral resource indicates that actual conditions once mining operations commence do not always mirror initial mine planning assumptions.

“In this case the bulk density of ore mined in the AF Gap and Fobinso pits is slightly different to what was assumed in prior mineral resource estimates and when this difference is factored into mineral resource calculations, it does have an impact, albeit, reasonably small,” explained Quartermaine.

He said that the recent infill drilling programme at Bokitsi South tenement has been successful in identifying mineable material with a head grade well above the LoM average ore grade.

Increase in ore grade

Quartermaine explained that this may lead to an increase in the average head grade of ore processed by EGM’s mill.

He says, “The grade of the Mineral Resources in the Bokitsi North and South deposits has increased from 2.6g/t to 3.0g/t and the amount of contained metal has also increased slightly.”

Further infill drilling is planned at Bokitsi South that will target extensions to the ore body to the south and at depth where the mineralisation appears to remain open.

An infill drilling programme is also currently underway at Mampong with the aim of delineating higher grade material and this will be extended to other deposits at Edikan in due course, subject to budgetary constraints, reports EGM.