The merger of ASX-listed companies Blackthorn Resources and Intrepid Mines will create a well-funded copper company that will see the completion of the Kitumba copper project in Zambia.
The merged group is expected to add significant value to the project that is currently undergoing a definitive feasibility study (DFS), with construction of the new copper project to begin in the first half of 2016.Paydirt conference
Speaking at the Paydirt 2014 Africa Down Under Conference, in Perth, Australia, last week, Blackthorn Resources CEO Mark Mitchell said the project had a $680-million capital cost and a net present value of $461-million. Mitchell also noted that the Kitumba project had a 11-year mine life and was expected to produce 56 000 t/y of copper.