Zambia’s energy minister on Monday called for dialogue between Copperbelt Energy Corp and Vedanta Resources to end a power supply dispute that has paralysed the British mining company’s operations, reports Reuters.
Copperbelt Energy on Sunday cut power to Vedanta’s Konkola mine for all but essential operations such as water pumping, ventilation and the operation of medical facilities.
Production affected
Konkola, one of Africa largest copper producers, has lost 482 tonnes of copper output worth $3.3 million after the power restrictions.
“Shutting down the concentrator has in turn affected production at our Tailings Leach Plant, which depends on primary material from the concentrator,” KCM said in a statement.
The restrictions to power supply at Konkola Copper Mines comes amid a dispute over an increase in tariffs by Copperbelt Energy, according to reports.
Electricity non-payments
According to Copperbelt Energy, Konkola had refused to make payments for the electricity it consumed between April 2014 to date, accumulating electricity bills totalling about $44 million.
Konkola last week lost a court application to stop Copperbelt, one of the biggest power suppliers to mines in Zambia, from cutting its electricity over the disputed bills.
Profitability impaired
The restriction of power supply was greatly impairing KCM’s production and profitability and may have implications for job security if prolonged, said the miner.
“Zambia’s copper production will go down with this restriction and Copperbelt Energy should sit down with Konkola so that our economy does not suffer,” Energy minister Christopher Yaluma told state radio.
Konkola, which produced 160 000 tonnes of copper in 2013, also owns a tailings leach plant, a smelter at Nchanga and a refinery at Nkana.