Murray & Roberts Cementation Zambia has reported completion of the sinking of the Synclinorium Shaft project in Kitwe, Zambia for its client Mopani Copper SynMines (MCM).

The new Synclinorium shaft will help significantly boost production and extend operations well beyond the current depletion dates at MCM – the largest copper mine in Zambia and one of the largest mines in the world.

“The last blast of the Main shaft took place on 30 September 2014 with the shaft at a final depth of 1,280.85m below the shaft collar,” reported project manager Neil Mackay.

Scope of work

The scope of work comprised a blind sink of a 7-metre diameter downcast-lined shaft with a bulk air cooler level, two electrical cubbies and two stations.

The equipping and commissioning of the shaft commenced at the end of October with the erection of a new headgear, winder and roping up the shaft scheduled for 2015.

The current date for commissioning of the shaft is December 2015, according to reports.

Common goal

The Murray & Roberts Synclinorium shaft team has worked closely with the Mopani Copper Mine Synclinorium Project team towards the common goal of helping the project reach the safe stage where it is today.

Noteworthy achievements at the Synclinorium Shaft project to date include a record 96m of sinking and lining achieved for the month of August 2013 and a Lost Time Injury Free figure of 290 days to date.

Challenges

A challenge to date has been the pumping of up to 24 000 litres of ground water daily from the shaft.

This groundwater is pumped to the surface from where it is diverted into a settlement pond for treatment.

“We intersected a 28 metre dyke, from 1 040 metre to 1 068 metre, and sank through it without incident, a notable achievement given that the rock is very hard and susceptible to scaling. This has necessitated support to within 1 m of the shaft bottom in order to increase worker safety,” Wyllie Pearson, senior project manager, Murray & Roberts Cementation Zambia, says.

Synclinorium equipment

Equipment deployed on the project by Murray & Roberts Cementation Zambia includes stage and kibble winders, a five-boom jumbo shaft drill rig, a five-deck working stage with a cactus grab, two mini excavators and an automated batch plant.

All equipment is serviced in a comprehensive on site workshop by a well-trained team to ensure operational excellence and adherence to stringent safety measures.

MCM innovations

Murray & Roberts Cementation Zambia introduced health and safety innovations at the Syclinorium Shaft project, which include the replacement of old hand signals and pull bells to communicate from the shaft bottom to the working stage platform.

The new system consists of a radio installed in a worker’s hardhat, with a built in speaker and microphone to enable hands free operation.

The shaft bottom signalling system allows the sinker at the shaft bottom to give the kibble winding engine driver signals from a hand held unit.

The Synclinorium Shaft represents Murray & Roberts Cementation Zambia’s first project for MCM from its Kitwe office where it has a 1 084-strong team.