Platinum producer Lonmin’s industry leading ramp-up in the aftermath of the prolonged platinum strike this year mitigated the loss of 391 000 in saleable ounces that resulted in revenue losses of about $500 million.

Lonmin’s revenue up to 30 September this year was $956 million a significant reduction when compared to $1.52 billion for September 2013.

Reducing capital expenditure

Lonmin said it is actively pursuing a process of allocating capital to projects that it believes will provide no less than 15% returns.

Taking into account risks, the miner seeks to reduce capital expenditure in line with cash generation.

“This year has been unique, with a strike of unprecedented length halting production for five months. Notwithstanding that, we have made progress in a number of areas. Our ramp-up exceeded all expectations and we are renewing our operational credibility,” commented Lonmin CEO Ben Magara in a statement on Monday.

The company will target savings and operational improvements and review its higher cost and more vulnerable shafts like its Hossy operation as it targets higher returns from its projects.

Short-term priority

Lonmin said its highest short-term priority is leveraging its ‘excellent’ Marikana operations.

The miner launched a comprehensive review of its assets and operations to address asset utilisation, reduce the total cost of ownership (TCO), improve capital efficiency and productivity and, therefore, profitability and cash flow.

As a result of the review, the miner concluded that its Marikana portfolio utilisation could be further optimised and its return on the limited capital invested, enhanced.

Ramp-up success

Lonmin said on Monday it lead the industry with an exceptional ramp up in a record two months following the platinum strike in the first five months of the year.

“We were bold in our approach to re-starting all our shafts. We prioritised shafts which would generate cash early, even though they may have been amongst our smaller and older shafts, before moving to our newer, bigger shafts some of which are higher cost assets,” said Lonmin in a statement.

All these measures have resulted in our small net debt position of $29 million as at 30 September 2014, leaving significant headroom to the $575 million in banking facilities available to the company.

The company said its efforts to reduce costs and improve profitability has identified value benefits of more than R2 billion over three years.

The next level

Magara said the company’s business review has surfaced ‘real opportunities’ to reduce costs, improve productivity and capital efficiency.

He said the company is seeing increasingly encouraging results in these areas.

“We have made significant management and operating model changes as we take Lonmin to the next level,” concluded Magara.