The final phase of an extensive crusher expansion and mill circuit upgrade project has been completed by Randgold Resources’ Tongon mine after dealing with an extended down time on one mill which had been down for 46 days, as a result of poor repairs to the journal and slipper pads.

“Tongon is now settling down well but the difficulties it faced over the past two quarters will have a negative effect on its production for the year. The management team has revised the 2016 business plan and is now targeting to exceed 260koz for the year.  It is worth noting, however, that it remains a profitable operation and, having paid back its capital in 2015, it has just declared a maiden dividend of $22 million,” said chief executive Mark Bristow.

The mine has also had to contend with an erratic power supply from the national grid and is set for improved performance in the second half of the year. A constructive engagement with the power utility has helped significantly improve the situation.

Bristow said during his recent tour of Randgold’s exploration sites in Côte d’Ivoire that the mining company had set its sights on further exploration in the country and that his team had identified attractive opportunities in the high-potential Boundiali and Mankono permits, as well as defined the potential for additional resources below the Tongon pit, as well as at some near-mine satellites such as Seydou and Sekala, which could extend Tongon’s life.

Bristow noted that Tongon has contributed $822.6 million to the Ivorian economy in the form of royalties, taxes, salaries and payments to local suppliers, and could very well expand the  continuing investment in the development of community health and education programmes and agricultural projects designed to provide post-mining employment.

Additional Reading?

Request Free Copy