South African platinum group, Implats and the Zimplats Board of Directors have approved the development of Mupani Mine at a cost of $264 million.
Mhembere said design capacity of 2,2-million tonnes per annum is targeted in 2025 when the full complement of ten mining teams will be deployed.
“At this rate, the new mine will have a life expectancy of some 25 years extracting only the relatively flat ore reserves.
“The project will increase Zimplats’ mineral reserves by 3 million to 9 million platinum ounces. Mupani Mine will employ approximately 1 000 people at full production and a substantial number of contractors will be employed during the development, construction and commissioning period to complete the project,” said Mhembere.
Once commissioned, the mined ore will be beneficiated in the state-of-the-art Selous processing facilities and smelted in the 12,5MW Zimplats furnace, which was recently equipped with modern remote controlled hydraulic mud guns for safe furnace tapping and upgraded furnace automation for online condition monitoring and safe process control.
“The operation has also ensured that all costs are kept to a minimum in the constrained PGM price environment, which has necessitated cash preservation strategies across the entire industry. Against this backdrop, we are delighted to approve and advance the new Mupani Mine,” said Terrence Goodlace, chief executive, Implats.
Goodlace said Mupani will sustain the mining operation well into the future and will ultimately support the group’s beneficiation strategy through securing the required future pipeline feed stocks.