The combined efforts of the Trans-Caledon Tunnel Authority (TCTA), Group Five and all subcontractors must ensure the prevention of acid mine drainage at Central Basin, writes Laura Cornish.
It’s a race against time. The new treatment plant at the Central Basin’s South West Vertical Shaft must be operational before acid mine drainage decants to surface. The acid mining drainage (AMD) dilemma, not a new concept to the South African public, reached emergency status when gold mining-acidic water started decanting from a defunct shaft in the Western Basin in 2002, polluting nearby spruits and groundwater. Today, the emergency is reaching critical status as government fights to prevent a repeat at the Central and Eastern Basins. Every day the water level shared between the three Witwatersrand gold basins – Eastern, Central, Western – is rising at a rate of about 300 mm/d, according to the Department of Water Affairs’ (DWA) Inception Report published in March 2012. Pumping stopped in the Western Basin in 1996, the Central Basin in 2008 and the Eastern Basin in 2011. Fortunately, the crisis on the Western Basin has been curbed thanks to the upgrade of the existing Rand Uranium plant, which has been expanded from 12 Mℓ/d to 36 Mℓ/d. This has stopped and neutralised the uncontrolled decant of water flows. The severity of the situation has seen government take an active stance. In 2010, the government formed an inter-ministerial committee to evaluate technologies and methodologies to best solve the problem – for the immediate future and the long-term future. TCTA, a special purpose vehicle established by the DWA, was appointed to implement the short-term intervention on its behalf. The immediate priority: the Central Basin The Central Basin extends from Durban Roodepoort Deep (DRD) in the west to the East Rand Proprietary Mines (ERPM) in the east. The mine lease areas in this basin extend over about 251 km2. Considering the amount of water necessary to treat the volume of AMD from the Central Basin is more than double that of the Western Basin, prevention (of AMD reaching the surface) is non-negotiable. Experts are predicting that water levels will reach the environment critical level around September/October this year – only 186 m below the top of the shaft. “If water rises above this level it could start having an impact on groundwater. The word ‘could’ is used as no one can accurately predict the hydrogeological reaction as the water level in the mine void rises,” explains TCTA business analyst Richard Holden. Construction of a high-density sludge treatment plant and pump system at the Central Basin’s ERPM South Vertical Shaft near Germiston commenced in February this year and marks another major milestone in government’s fight to prevent AMD entering the Vaal river, which would ultimately cause a shortage of water to consumers in Gauteng and the surrounding provinces. “Without this project, the major impact will be on water security for anyone who draws water directly or indirectly from the Vaal River system,” Holden notes. During the due diligence, various shafts were evaluated and given the cost to construct a new shaft, an existing defunct shaft was chosen. The plant will be situated at the existing South Vertical Shaft, which intersects the mining void of the central basin. The eastern side of the Central Basin also represents the lowest pumping head. For TCTA, allocation of sufficient funds to enable the construction contract to be awarded, coupled with obtaining environmental authorisation where legislation has never made provision for this type of project, have been significant challenges Holden explains. Regardless, the urgency of the project has necessitated TCTA bring its strengths to the table: funding and implementing large-scale water projects. “Thanks to much negotiation and compromise with ERPM, Central Rand Gold, the Department of Environmental Affairs, the DWA and all the interested and affected parties who participated in the scoping report, the success of this project will become a reality.” Group Five Civil Engineering was appointed the full R319 million treatment plant construction contract, including civils, earthworks, building, and mechanical and electrical installation. It will be three times larger than the next biggest similar treatment plant in South Africa (at eMalahleni), with highly complex concrete structures, piping and electrical systems. Holden says the plant is designed to treat 57 Mℓ/d. “At this stage the final ‘treated’ effluent will still have a high sulphate content (approximately 200 mg/ℓ). This is no different to what was discharged by the mines up until to 2008 when pumping and treatment at this site ceased. The stream bed is already heavily polluted from old tailings and urban stormwater run-off. Although this is not ideal, it is still a lot better than doing nothing until a long-term solution has been completed.” The biggest impact caused as a result of the project is the increase to the salinity of the water in the Middle Vaal system, which necessitates the release of fresh water from the Vaal Dam to dilute it. “This will result in a deficit in the Upper Vaal system in 2015. What this means is that if there is a drought, water restrictions will need to be imposed.” Wayne Poulsen, senior site agent for Group Five, explains the basic treatment process: “An extraction pump station, including two huge dewatering pumps, will pump AMD from the existing ERPM shaft. The water will be pumped to two reactors, which combined have an 80 x 80 m concrete footprint and are 5 m deep. This water is then pumped to a lime dosing plant, including silos and eight mixing tanks, each of which are 16 m in diameter and 4 m high. Two thickeners, each 47 m in diameter, will settle out the solids. The treated water will be discharged via pipelines to the nearby Elsburg Spruit and the sludge discharged via pipeline to an existing ERPM tailings facility.” Group Five is further responsible for the construction and delivery of all ancillary tanks and buildings as well as a full-scale laboratory. Ekurhuleni Metropolitan Municipality will supply the necessary clean water to site and power will be provided via a high-power 4 km overhead line. “Our construction timeframe is less than a year, meaning not a day can be wasted. Trial commissioning will start in November 2013 , with trial operations running until 18 April 2014,” Howard Wakefield, senior contracts director for Group Five Civil Engineering points out. “We will hand the plant over to TCTA at complete readiness after which it must run permanently, 24/7. Our most critical challenge throughout the project remains time; we have to meet our critical deadlines. But we are confident of success; we started well and are making excellent progress.” Wakefield believes that even though there were numerous tender bids put forward for the project, “our combination of pricing, technical ability and compliance with TCTA’s stipulated requirements for enterprise development and BEE (including mentorship, procurement, employment, enterprise development and skills training) ranked us highest”. Current project status Earthwork construction on site is well under way, says Chris Prinsloo, general manager of Diesel Power’s Civils & Bulk Earthworks Division. Primarily a mining contractor, Diesel Power is focused on growing the civils arm of its business. The company is responsible for all project bulk earthworks, from excavation through to platform construction and backfilling. Prinsloo admits that their challenge, like Group Five, is time. “It is a tight programme and we need to hand over the platforms so the next let of the project can start. We have also been experiencing a lot of rain. Regardless, our commitment to the project is unwavering, and we will meet our deadlines.” The company has eight staff members, 20 operators and 16 labourers dedicated to the job. “The reactor platform is already completed, the thickeners area is 70% complete, the dosing area is 60% complete and building platforms are 80% complete,” says Prinsloo. “We have also just started on building the internal roads and the retaining walls.” Plant on site includes:- 4 excavators
- 1 dozer
- 1 grader
- 2 rollers
- 2 water trucks
- 22 tip trucks
- 1 tlb
- 1 front end loader.
“Projects such as this are extremely complicated and do not naturally fall into the category of national water resource, water board or municipal responsibility. They are a prime example of integrated water resource management and will shape projects to come as South Africa reaches the limit of its allocable water resources. They need time to come together to ensure that they are environmentally and financially sustainable,” Holden reiterates.
Sidebar: Key role players- Responsible government department Department of Water Affairs
- Implementing agent TCTA
- Design Aecom
- Main contractor Group Five Civil Engineering
- Piping Murray & Dickson Construction
- Earthworks Diesel Power
- Mechanical S.A.M.E
- Electrical Standard Electrical
- Civil foundations M3 Construction
- Building and civil works Enza Construction
| Western Basin | Central Basin | Eastern Basin | |
| Volume of AMD that needs to be treated | 27 Mℓ/d | 57 Mℓ/d | 82 Mℓ/d |
| Environmental critical level (ECL) | 1 550 m AMSL(165 m BCL) | 1 467 m AMSL(186 m BCL) | 1 280 m AMSL(290 m BCL) |
| Current level | 0.88 m BCL | 256 m BCL | 423 m BCL |
| Breach of ECL if pumping does not commence | Breached already. Objective is to draw the water down to ECL | Sep/Oct 2013 | Nov 2014 |
| Location of treatment plant | Rand Uranium, Mogale City | South West Vertical Shaft, Germiston | Grootvlei No 3 Shaft, Springs |