Anglo American’s Kumba Iron Ore has held an official handing over ceremony for its R1 billion Life-Of-Mine Heavy Mining Equipment (HME) workshop at its Sishen mine in Kathu in the Northern Cape.

“Today is a very significant event for Sishen, because the HME Workshop is also symbolic of Sishen’s future,” said Sishen’s Johan van Schalkwyk at the event.

The facility is expected to cater for the mine’s equipment maintenance and service needs for the next ten to 15 years.

The project started three years ago when an economic evaluation determined that a lot more value could be generated by Sishen through the exploitation of some of its deeper ore reserves.

This meant increased stripping ratios and hence increased material movement requirements as the mine ramps up to a target of 300 million tons a year.

The new HME Workshop has a footprint size of 8 758.6 square metres for the total facility, excluding the apron. It is 28 m high and 52 m wide, with a length of 172 m.

A total of 1 581 tons of structural steel was used in its construction, sourced from a Chinese fabricator.

The HME Workshop has adequate crane capacity to accommodate Sishen’s first new ultra-class Komatsu 960E trucks.

This has meant that Sishen’s haul-truck fleet can now be increased from 75 to 156, together with a significant increase in the size and load-carrying capacity of the haul trucks.

TWP (now WorleyParsons RSA) and Bvi were appointed as engineering consultants for the pre-feasibility and feasibility reports in October 2010.

They were tasked to investigate methods to fast-track the design, procurement and implementation of the project, which took three years to plan and 17 months to build.

“The aim was to find an optimised solution to cater for the additional service demands. We also needed to ensure the sustainability and improvement of safety and operational standards,” said Hamish Riddet, TWP project manager.

“To achieve this, we investigated the bulk infrastructure for the new tyre workshop and associated services, because the development of new infrastructure is an essential part of future expansion,” said Riddet.

The previous tyre-fitting workshop had no floor and roof, and was too small for haul trucks. The new tyre workshop, with tyre-removal bays, storage areas and other bulk facilities, is essential for future and secondary fleet expansion.

Traffic congestion in and around the existing diesel workshop, which was a major safety risk, has now been reduced thanks to the design of the facility.

Travelling time to maintenance facilities has also been reduced to add another cost and safety benefit, while also providing safe access from mining operations for equipment.

Although a few days were lost due to strong winds during July, the project was a success and was completed ahead of schedule and under budget.

A major milestone was the one million lost time injury (LTI) free hours and 500 LTI free days achieved by the team during construction.

Speaking at the official handing-over ceremony, WorleyParsons RSA CEO Digby Glover said: “We are proud of the facility and the success we have achieved here.”

Stefanutti Stocks MD Schalk Ackerman said the project was a first for the South African mining and construction industries in that it had combined earthworks, concrete, mechanical and electrical and building works “on a fully integrated basis, with one management structure.”