The remaining sulphide circuit at Randgold Resources’ Kibali gold mine in the Democratic Republic of the Congo (DRC) is scheduled for completion at the end of Q1 2014, chief executive Mark Bristow told a media briefing in Kinshasha. Production will commence in 2015.
Shaft-sinking is underway at the complex’s underground mine, and the first of four hydropower stations due to be commissioned soon.
Bristow said that Kibali “is expected to exceed its gold production for its first full quarter of operation, the three months to December, and meet its forecast of 55 0000 ounces for the current year.”
Like all the other gold mines Randgold has developed, it should also make a net profit in its first quarter, he said.