MDM Engineering has been awarded the definitive feasibility study (DFS) for Royal Bafokeng Platinum’s (RBPlat’s) 250 000 tonnes per month (tpm) Merensky upgrade at its Bafokeng Rasimone Platinum Mine (BRPM).
The BRPM concentrator is a joint venture platinum operation between RBPlat and Anglo American Platinum. It was initially designed to treat 200 000 tpm of Merensky ore.
MDM has also been awarded a second DFS for the stand-alone 100,000 tpm Merensky concentrator, which is to be erected adjacent to the existing BRPM concentrator.
Principal study manager Jeff Stevens said the project management company was “thrilled to be working on yet another PGM project.”
This follows the successful construction and commissioning of the Tharisa expansion project in 2012.
“MDM’s PGM execution and study experience will bring a large body of knowledge to the BRPM projects. We look forward to building on our strong working relationship with the stakeholders of these projects,” said Stevens.