Construction on the Grootegeluk Medupi Expansion Project (GMEP) is now 97% complete, Exxaro has stated in its 2013 results.
The project will supply Eskom’s Medupi power station with 14,6 million tonnes per annum (Mtpa) of coal.
The coal supply ramp-up began in 2013, with 1.3 Mt produced and 0.9 Mt dispatched to Matimba power station after industrial action affected the mine’s production in Q1 2013.
Further ramp-up and performance testing will be done in the first half of 2014 as per the revised contractual arrangement.
GMEP outstanding mining equipment that was delayed on the back of the revised ramp-up schedule agreed between Exxaro and Eskom has been provided for in Phase 3.
Total project expenditure to date is R9,3 billion, with total capital expenditure forecast at R10,2 billion, including GMEP’s portion of the houses and backfill project.
The backfill project has progressed well, with Phase 1 completed in 2013. It is expected to be operational in the Q1 2014. Phase 2 is planned to be completed by the end of 2017.