Despite identifying potash as a potential strategic ‘fifth pillar’, BHP Billiton has pushed out timelines for its Canadian Jansen project by almost a decade.

Global mining group BHP Billiton has high hopes for the future demand of potash, but has decided to adopt a “measured approach” to the development of its Jansen project.

The company issued an operational review for the nine months ended 31 March 2014 on Wednesday, reporting record production for commodities including core resources iron ore and coal.

BHP Billiton previously indicated that potash could become a ‘fifth pillar’ in its much publicised ‘four pillars’ strategy, but now seems to be favouring slower development as part of its cost cutting and productivity agenda.

The Jansen potash project in Canada, which the company has spent $2.6 billion so far developing, has been described by BHP as “the world’s best undeveloped potash resource”. The company believes the project is likely to be one of the lowest cost sources of supply once fully developed.

But despite its apparent potential, the Jansen mine is not being ramped up as quickly as BHP Billiton previously indicated.

According to the update, shaft excavation resumed in the March 2014 quarter and progress is continuing, but at a “measured pace”. As a result of this restrained approach, the level of expenditure in the 2014 financial year is expected to be approximately 25% below the prior guidance of $800 million.

The company has revised previous targets of completing both shafts by 2016, saying the shafts are no longer expected to be completed in this timeframe. It has now phased out the ramp-up of the project to well beyond 2020.

“This does not affect our $2.6 billion budget or longer-term development plans as the shafts are not on the critical path. On the basis of our current projections for market demand, the Jansen mine could ramp-up to its theoretical design capacity of approximately 10 Mtpa in the decade beyond 2020,” the company said.

In an earlier release on its investment in Jansen, BHP Billiton indicated a strong long-term outlook for potash – a fertiliser that improves the yield of agricultural production.

“As the world’s population grows and incomes in emerging economies improve, agricultural demand is expected to rise. This will increase the need for potash and require the construction of new mines,” the company said in August last year.

On Tuesday stocks of the world’s biggest potash producer, PotashCorp, rose for a second day, following media reports that BHP planned to make another bid for the company.

In 2010 BHP Billiton attempted a $38.6 billion hostile takeover of PotashCorp, but failed due to the Canadian government blocking the bid. Neither of the companies has commented on recent market speculation.