The Democratic Republic of Congo’s (DRC’s) ambitious aim to double mining output over the next five years has seen a new JV signed between a leading private investor and construction company to develop new infrastructure projects in the DRC.
Fleurette has been investing in the DRC for 17 years, with core expertise in executing projects in mining and related sectors. It also has a proven track record of successful cooperation with key stakeholders and partners in the region.
Andrade Gutierrez is a leading global construction company, with over 65 years’ experience in developing engineering projects worldwide. It has operating experience in ten African countries. It provides expertise and support along the development and post-construction lifecycle, including operation and maintenance. Key projects completed successfully include, over the past 12 months, the delivery of 200 MW of thermal power plants, four airports and several roads projects in sub-Saharan Africa.
Investment bank
The JV has appointed Renaissance Capital, a leading frontier-markets investment bank, as financial advisor. The JV will evaluate different investment opportunities and projects in which the companies can work together to develop and then take the project forward to completion. Andrade Gutierrez will act as the lead developer in any chosen project. The JV is not seeking a partner to bring an existing project to fruition.
While considerable progress has been made in the DRC to develop the economy after years of conflict, the country remains in need of significant investment in its infrastructure to further its economic development. The JV will target opportunities in the power, rail and road sectors, all of which will hugely benefit from new investment.
Major power shortages force the DRC to import energy from outside the country, while total installed capacity has remained level for 20 years, despite significant increases in demand, both industrial and commercial.
Economic growth
In the Katanga region, the engine of the DRC’s economic growth, power supply is about 500 MW, including imports from Zambia. Demand in the region is currently 650 MW to 750 MW, and is expected to reach 1 000 MW, with the doubling in mining output planned in the next five years. With mining activities already constrained by power shortages and the expected increase in the needs of the general population, there is an urgent need for new power supply.
The DRC’s rail network is of primary importance for shipping mineral commodities out of the DRC to ports in east, west and southern Africa. Road infrastructure will soon be insufficient to transport the increased mining output, at about 400 trucks a day. An improved rail system will significantly reduce transportation costs for the resources sector and vastly increase general transport efficiency for the entire country, taking trucks off the road system.
Finally, the DRC’s road network has fallen into serious disrepair as a result of its extended period of conflict. Sealed roads comprise a mere 3 000 km of the country’s total road network of over 30 000 km. It is estimated that just 42% of the country’s roads are in a condition good enough to support freight transport. The World Bank estimates that repairs and maintenance on the DRC’s existing road networks will require roughly US$400 million a year.