Gold production for the March 2014 quarter fell by 12% to 8 368 kg, from 9 515 kg in the December 2013 quarter, Harmony Gold has reported in its results for Q3 FY14 and for the nine months ended 31 March 2014.

CEO Graham Briggs attributed the decline in the quarter-on-quarter production to production stoppages at Doornkop due to the fatal accident there in February this year, flooding of the shaft bottom at Joel and a slower turnaround and technical isseus at Kusalalethu.

Production at Steyn 2 was suspended six months earlier than the planned life-of-mine, due to increased seismicity in the working areas.

Increase in underground recovered grade

However, Harmony’s underground recovered grade increased for a third consecutive quarter, and was 5% higher at 5.10g/t, compared to 4.85 g/t in the December 2013 quarter.

Lower gold production slashed 6% off the company’s production profit, from R986 million in the December 2013 quarter to R924 million in the March 2014 quarter.

Higher average gold price

The 13% decrease in gold sold was offset partially by the higher average gold price received, resulting in revenue decreasing by only 6%.

Production costs were lower mainly due to inventory movements and cost-savings. As a result, gross profit was at a similar level compared to the previous quarter.