Shaft Sinkers Holdings has announced that the main shaft at the Kibali gold mine in the Democratic Republic of Congo has exceeded 500m in depth.

“The main shaft sinking is progressing very well, and has reached the major milestone of 500 m, with sinking proceeding at a rate of at least 3 m/day for more than 30 continuous days,” said CEO Alon Davidov.

3m/day for 30 days

The South Africa headquartered and London quoted specialist shaft sinking contractor has updated its progress on the project, which is ramping up to be one of Africa’s largest gold-mining operations.

Kibali is a joint venture between mine operator Randgold Resources (45%), AngloGold Ashanti (45%) and Congolese parastatal Sokimo (10%). Randgold is responsible for mine development and operation. It poured its first gold ahead of schedule in September 2013.

Joint open pit, underground mine

Kibali is being developed as a joint open pit and underground mine. Current production is from its open pit and an oxide circuit. Commissioning of the sulphide circuit started during the past quarter, while development of the underground mine remains on track, with the vertical shaft having reached the halfway mark and the first underground ore accessed.

The mine has reserves sufficient to see it producing at a rate of around 600 000 oz/year of gold for at least ten years.