Ground-breaking at the Asanko Gold Mine plant in Ghana is expected to commence in August 2014, pending a positive investment decision on the project by the board in July.
The site early works programme, which began in April 2014 with a budget of about $16 million, has been progressing on schedule and on budget. DRA is EPCM contractorIn early April, Asanko engaged DRA as the EPCM contractor for the design and construction of Phase 1.
Knight Piesold will design the tailings storage facility and carry out detailed geotechnical engineering works. An early works programme was subsequently initiated, designed to advance the critical activities that will allow Asanko to maintain its project schedule, targeting first gold in Q1 2016.