Following a completion of the Liqhobong Diamond Mine financing in May 2014, Firestone Diamonds reports that the construction and development programme at the Lesotho Highlands is expected to take 24 months.

The company reports that nameplate production of 300 000 tonnes is expected to be achieved in the first half of 2016.

Development on budget

The build and commission of the Main Treatment Plant and supporting infrastructure at Liqhobong has commenced in order to ensure it is delivered in H1 2016 and on budget, reports Firestone.

The development programme is being executed by Firestones project team and led by the chief project officer, Glen Black.

Firestone reports that approximately 73% of the EPCM budget has been committed to date. The company reports that major equipment deliveries are aligned to its current baseline schedule.

“I am pleased to announce commencement of the earthworks programme at our Liqhobong diamond mine in Lesotho, which follows the recent completion of the financing,” commented Firestone CEO Stuart Browne.

Project highlights

The Liqhobong project earthworks, including civils and earthworks and Residue Storage Facility contracts have been signed or agreed.

Decommissioning and removal of the Pilot Plant at Liqhobong underway and 30% complete, reports Firestone.

In addition, the overhead power line and main substation contract is signed and site mobilisation has been initiated, with major equipment long lead items have been approved and contracts placed.

Other project highlights include major equipment deliveries aligned to current schedule.

General site earthworks have commenced and includes widening and rerouting the site access road, and building the residue slimes retaining wall and early civils works.